吊钩式抛丸机安装试机注意事项

- 2021-06-03-

吊钩式抛丸机一般外观较大,安装过程相对比小型设备复杂。正确的安装和试机是保证后期设备正常运行的关键。在初次操作不熟练的情况下,请用户严格按照相关人员的指示或参照使用说明进行操作。未经授权的操作很容易造成不可逆转的损坏吊钩式抛丸机. 这shot blasting machine manufacturer has sorted out the precautions for installation and test machine to share with you. I hope it will be helpful to users who use the device for the first time.
1. Installation. 这吊钩式抛丸机 is installed and debugged in the production plant and disassembled into several parts before being transported to the user site for installation. Although there is no pit, the foundation must be firm, the anchor bolt holes must be standardized, and the chamber body must be adjusted. After the second irrigation, the anchor bolt nuts can be tightened after solidification. After the chamber body is fixed, the various parts can be installed. 这precautions for the installation and debugging of the relevant components are introduced below.
1、抛丸装置:
这shot blasting device has been installed on the chamber body before leaving the factory. Please pay attention to the problems to be debugged before use. Check whether the fixed positions of the blade, the pill wheel, the directional sleeve, and the guard plate are accurate and firm, and check whether the direction of rotation is correct after power on. Then adjust the position of the directional sleeve opening. Theoretically, the angle between the front edge of the directional opening and the front edge of the blade throwing position is about 900. After fixing the position of the directional sleeve, the position of the projectile belt can be detected by hanging Place a steel plate or wooden board on the position of the workpiece facing the exit of the shot blasting machine, start the shot blasting machine, put a small amount (2-5kg) of projectiles into the blasting tube, and then stop, check whether the hit position on the steel plate is suitable for the needs, such as Close the window of the bias-adjustable directional sleeve downwards, and vice versa, until it fits, and note the position of the directional sleeve opening as a basis for future replacement of the directional sleeve.
2、提升机和螺旋输送机:
首先进行空载试验,检查提升斗和螺旋叶片的运行方向是否正确,然后将提升机的皮带张紧到适度的张紧度以避免跑偏,然后进行负载试验检查运行和输送能力,是否有任何异常噪音和振动,检查并清除障碍物。
3、丸砂分离机:
先检查闸板运动是否灵活,再检查隔板位置是否正确,然后在葫芦装车调试时,是否有钢丸不断流入,检查是否有钢丸流出和落下当溜槽卸料时